Work has reached first floor roof level.Flat roof portions in the rear will be concreted on 27/10.Work will then start on slope roof above front Gym room and upper lounge and part of Home Theatre.Pictures show work in progress
4500 sft house being constructed at Jackanarai village near Ootty in Tamil Nadu for Mr.Saravanan,Software Engineer working in USA
Monday, October 26, 2009
Monday, October 5, 2009
Brick work reaching lintel level at First Floor
Brick work has reached lintel level at First Floor.Precast outside stair steps are being fixed.Ground floor front side slope roof concreted.
Pictures show work in progress and me standing at open terrace area in the front side of the house where ground floor slope roof come up to become parapet for open terrace area.