Saturday, June 27, 2009

Foundation work reaching Ground Level
















After earth work excavation for column footings,Column footing concrete and column pedestal concrete is completed.Sand filling done upto newly fixed Ground level.Plinth beam work is now in progress

Monday, June 1, 2009

Foundation work progressing







Earth work excavation for column footings completed.Basically the soil is hard laterite in nature.But in the front side,there is an area where soil filling was done previously for flower cultivation.Hence the front columns have to start at a bit low level
Pictures show view from the house construction site and excavated areas for column footing.In the excavated area,sand filling and floor concrete is done.Column footing concrete is now in progress